Alex has 27 years of loss adjusting experience and has worked extensively on major and complex loss claims in the UK, Australia and across the Middle East. He has also served on a number of Catastrophe response teams in the Caribbean, the Bahamas and at various locations in Australia.

Alex has dealt with numerous high value and complex construction and infrastructure claims (first party and third party) under a variety of industry specific insurance arrangements including: CAR / EAR Policies; Project Specific and Annuals; Owners Controlled Insurance Project (OCIP) Comprehensive Project Insurance Policies; Civil Engineering Completed Risks and associated Liability and Professional Indemnity covers.

He is the directly nominated adjuster on a number of Project specific and Annual policies and is well versed in application and interpretation of the various LEG and London Market (DE) Design Exclusions.

Alex was a Senior Construction & Engineering adjuster with Lloyd Warwick International’s Corporate Partner (Crawford  & Company) in the UAE for a 7 year period from 2008 to 2014 and was responsible for UAE adjusting operations from 2012 – 2014.  Being latterly based for 5 years in Abu Dhabi, Alex was responsible for a number of the company’s Oil & Gas Project nominations.

Power & Energy

  • Explosion, Ethane Rich Gas Compressor in NGL plant
  • Collapse of Process Plant in Petrochem Olefins Conversion Unit
  • Impact, Offshore Water Injection Tower
  • Explosion in Nitrogen Receiver at Gas Plant
  • Vacuum in Neutralization Tank at Petrochem Plant
  • Repositioning Offshore Platform following loss of hole
  • Damage to Caissons, Offshore Gas Processing Platform
  • Deformation of crude oil storage tank roof deck
  • Vessel impact damage to 30 inch flare line
  • Fire in Gas Turbine combustion chamber
  • Fire and BI, Gas Turbine air intake filter house
  • Catastrophic failure of 500 MVA auto transformer
  • Flashover damage to rectifier transformers at Aluminium Plant
  • Failure of Air Compressor in Air Separation Unit of Nitrates Plant
  • Degradation of pipeline coatings, LNG Project
  • Machinery Breakdown, Electrical failure of Generator rotor
  • Damage to Gas Turbine Compressor Package during maintenance
  • Machinery Breakdown, Damage to Heavy Duty Gas Turbine

Industrial and Heavy Engineering

  • Fire and BI, Steel DRI plant
  • Machinery Breakdown and BI, Steel DRI Plant Process Gas Heater
  • Machinery Breakdown and BI, shoe bearing Cement Mill
  • Fire and BI, cooling water tower in steel plant
  • Molten Metal Breakout, steel melt shop Continuous Casting Machine
  • Storm Damage at Desalination Plant
  • Damage to Ship loader and Stockpile Stacker at Coal Export Facility
  • Cyclone Damage, Sediment Ponds and infrastructure at Coal Terminal
  • Hail Damage, collapse of Distribution warehouse
  • Flashover of Gas Insulated Switchgear at Desalination Plant substation